|
|
||
|
|
Waterpower Projects
Waterpower Case Study: Bracebridge Generation
The Project: A water power generation facility located in Bracebridge, Ontario, utilizing river water.
Because deregulation of the electricity market in 2002 required generation to be owned by a company other than the local utility, Lakeland was formed as a holding company with the municipalities as shareholders. The electrical assets of the municipalities were merged and the generating component was separated. Bracebridge Generation owns and operates four water power plants.
Including other plants, a total of 3,500 homes are supplied by water-generated power from Bracebridge Generation. Information Source: Information was supplied by Mr. Chris Litschko, President and CEO, Bracebridge Generation Ltd. Project Goal “When the original High Falls plant was constructed in the 1940s, the developers realized that it had greater potential and poured a concrete base foundation to allow for future expansion,” says Chris Litschko, President and CEO of Bracebridge Generation. “Coupled with the fact that the site was already owned by the company, this gave the project a distinct advantage over a brand-new facility. At the same time, in terms of approvals, planning, etc., we went through exactly the same processes as if there were no existing plant.” Assessment and Approvals
“With the municipalities as partners in the project, gaining municipal approvals and permits generally presented few problems,” Litschko says. “Also, a licensing agreement with the Ontario Energy Board was already in place for the existing plant, and distribution connection requirements with Lakeland Power presented no serious problems.”
“Even with the help of a consultant, gaining approvals took almost two years,” Litschko says. “We would advise prospective developers to assume 18 months to two years for approvals before construction can begin. Also, the costs of approvals for the project were about $250,000, and we can't see these costs changing regardless of the size of the project.” Business plan and financing
“While the project was not dependent on incentives, our planning assumed that the Government of Ontario's support for renewable energy projects would result in a program that would justify the investment. This is why the Standard Offer Program, which provides a 20-year contract with a guaranteed price, was critical to our project.”
“The bank offered terms that were as good or better than most federal or provincial funding programs, with less complex and time-consuming approvals processes,” Litschko says. “A federal loan was applied for and approved, but its covenants were too restrictive for us to accept.” The total cost of the project was $4.8 million, even though a concrete base, dam and headpond for the plant were already in place, which saved construction costs.
Annual electricity: 10,000,000 kWh Simple Payback: four years ConstructionThe developers used a consulting engineering firm who divided the project into construction and generation equipment installation, which meant that the construction contractor had to coordinate with the equipment contractor. The total time from the start of construction until the new plant came into operation was one year. Lessons Learned
“Also, NIMBYism will slow down the project no matter what you do. Many NIMBY concerns are legitimate and can result in a better project, but some just want to fight and make sure the project is never completed. Litschko also advises that construction material costs are rising, although generators are steadily improving in efficiency. He adds that building contractors should have a high financial daily penalty to ensure that timetables are met. |
|